PMI’s recommendation for passing the PMP Exam is to practice the exam experience. This is a full-length practice exam that is NOT timed. The purpose of this practice exam is to be able to take your time with the practice exam questions and to focus on understanding why an answer is correct. This practice exam is configured to provide immediate feedback for each question, indicating if it is correct or incorrect. The feedback for each question will also be displayed.
If you want to simulate the PMP Exam, take one of the Timed Practice Exams
0 of 180 Questions completed
Questions:
You have already completed the quiz before. Hence you can not start it again.
Quiz is loading…
You must sign in or sign up to start the quiz.
You must first complete the following:
0 of 180 Questions answered correctly
Your time:
Time has elapsed
You have reached 0 of 0 point(s), (0)
Earned Point(s): 0 of 0, (0)
0 Essay(s) Pending (Possible Point(s): 0)
You did not reach a passible score on this attempt. We recommend you take this Practice Exam until you reach at least a 90% score. Remember, the actual PMP exam will be more difficult. You should be as prepared as possible before sitting for the actual exam.
You have reached at least a 90% score on this Practice Exam. While this is a good score, we recommend you continue to practice until you are fully confident in your ability to pass the actual PMP Exam.
The Project Management Office wants to offer constant reporting across the dozens of agile projects running concurrently. They want to use information radiators to share progress status and key lessons learned.
How can this best be achieved?
After three agile iterations showed a trend of increasingly prolonged test work, the team performed an intensive backlog refinement.
What metrics would show that the problem was effectively addressed?
A government is ready to announce a new tax on sugary products to fund a healthcare program. The team is working on the first set of goals to secure buy-in from the industry stakeholders and launch a strong public campaign to support the mandate.
In which three ways can the project build a shared understanding of the project goals with public stakeholders? (Choose three)
A project manager is facilitating a workshop to define the “Definition of Done” (DoD) for a new digital product. The development team insists that the DoD should focus on code quality and unit testing, while the product owner insists it must include user acceptance testing (UAT) and marketing approval. The two groups are reaching an impasse, and the disagreement is delaying the start of the first sprint.
How should the project manager handle this situation to build shared understanding?
A project manager went on a vacation and returned to discord. According to two stakeholders, stakeholder C is causing problems. Every day for the last two (2) weeks, stakeholder C sent an email to the team, checking progress and giving new instructions. The team ignored the emails and continued working, but the other stakeholders are concerned about stakeholder C’s behavior.
What should the project manager do?
A project’s goal is to improve a company’s customer service process through automation and staff development. The team sent initial surveys to the staff to assess their satisfaction with the current process and are now analyzing the responses. These are the top four responses:
• The current process works fine.
• The current process needs fixing.
• We need better training.
• We do not need any more training.
Which two activities should the project team perform first? (Choose two)
A project manager is leading a global team on a time-sensitive product launch. Two team members from different regions have a recurring disagreement regarding the specific format of the weekly status report. The conflict is starting to consume significant time during their 15-minute daily stand-up meetings. Because the product launch is only two days away and every minute is critical, the project manager tells the two team members, “We will use the current format for the next two days to stay focused on the launch, and we will sit down next week to design a new format together.”
Which conflict resolution technique did the project manager apply?
A project team is small, and the team members have known each other for a long time. The team’s project is in the execution stage. Recently, a team member told the new project manager that another team member has been complaining about how the project is being managed.
How should this new project manager respond?
A new project team is setting early priorities, and they plan to gain the customer’s trust by delivering value as quickly as possible. Team member C mentions that they have worked with the project sponsor on other projects.
How should the project manager connect these two facts and create an advantage for the project team?
Leaders of high-performing project teams __________ team members’ skills and knowledge and keep team members __________ throughout the project.
Fill in the blanks with the correct set of responses.
The agile team is composed of highly skilled product design engineers. Their reputation for quality and speed has earned them new duties in concept development for new products, but team output in this new role has fallen steeply compared to their design work.
Which two measures are most effective to improve team productivity in this case? (Choose TWO.)
A project manager experienced in predictive methods is taking on an agile project for the first time. To help in making a successful transition, the project manager makes a list of situations that may arise from inadequate action as a servant leader.
Which three situations would be on this list? (Choose THREE.)
A collocated agile team is updating the ground rules based on the last iteration and retrospective.
Which option should be excluded from the new ground rules?
A project manager is leading a cross-functional team that has recently started working together. During the first few weeks, the project manager notices that several team members are arriving 10 to 15 minutes late to the daily stand-up, causing the meeting to run over its 15-minute timebox and delaying the start of the day’s work. What is the best way for the project manager to handle this situation?
The IT department of a glassware manufacturer enthusiastically approved the agile team’s mid-project demo of quality-checking software for assembly line workers. However, the final product was considered UNUSABLE because the workers’ gloves are too thick to press the machinery’s small buttons.
What should the project manager do to avoid this kind of failure in the future?
An agile team welcomes a new team member who is unfamiliar with the agile approach. At the weekly demo meeting, this team member becomes visibly nervous when an operations engineer, who often criticized their previous work, appears unexpectedly and gives very direct feedback about the prototype. After the meeting, the new team member leaves the room quickly.
How should the team respond?
A project manager is leading a newly formed agile team. During the last two retrospectives, the team members expressed frustration because they felt their technical decisions were being constantly questioned by a senior stakeholder who is not part of the daily stand-ups. This has led to a decrease in team morale and a slowing of the sprint velocity.
How should the project manager handle this situation?
A project manager with limited experience managing globally distributed team members is appointed to a project with team members who are all from another country and speak a different native language.
To successfully manage this project, the project manager needs to have cultural sensitivity.
What of the following actions should the project manager NOT take?
A financial software company serves stock markets worldwide. An experimental quality assurance project has agile teams working in three company offices: Seattle, Tokyo, and London. The teams work in two shifts in each location at the following times in each time zone:
Shift 1: 08:00h to 16:00h
Shift 2: 16:00h – 0:00h
Which collaboration method would ensure the fastest “follow-the-sun” problem resolution?
A company is constructing recycling plants in fifteen (15) countries around the world. The lead in the project management office (PMO) wants more timely progress reporting and experience sharing between project managers in each of the geographically distant projects.
Which two agile methods might the PMO use to fulfill this need? (Choose TWO).
A project manager is reviewing the performance metrics of an agile team and notices that while the team’s velocity is high, the “rework rate” has increased significantly over the last two months. During a private conversation, the Quality Assurance (QA) lead mentions that the developers are rushing to meet sprint goals and are bypassing some unit testing protocols.
What is the best action for the project manager to take to support team performance?
Project A is experiencing schedule performance issues. After assessing the issues, the project manager determines that project resources have low expertise levels.
Specifically, a few of the senior-level resources perform irrelevant work, and some inexperienced resources take too much time to complete tasks.
Which action should the project manager take to enhance team performance?
A project team has been efficiently delivering results. The product upgrade they are working on must be released in three months or else a competitor’s new product will make theirs obsolete. Citing this reason, the product owner makes a sudden request for a feature revision. However, no one on the project team is capable of doing the work. The project sponsor is willing to extend the budget but CANNOT extend the schedule.
What should the project manager do?
An agile approach is required during the final phase in a team’s project. As the team discusses the phase, some team members disclose that they have NOT worked with agile before. The deadline is approaching soon.
How should the project manager respond?
During Project A’s kickoff phase, the project manager provided training for the entire team regarding the specifics of the company operations that the project supports.
A year later, project productivity is suffering because members who were added later in the project do NOT have the same level of understanding.
How should the project manager respond to this challenge?
A high-influence stakeholder frequently contacts individual developers directly to request minor “tweak” changes to the user interface that were not included in the original requirements. The developers, wanting to be helpful, often perform these changes without informing the project manager.
What should the project manager do to empower the team and stakeholders while maintaining project integrity?
A project is comprised of three highly dependent parts, each being completed by its own project team. The team leader, worried that conflicts might arise when the outputs from the three teams are combined, asks for advice.
What advice should the project manager provide?
A project team is comprised of local and virtual team members. To manage scheduling priority conflicts among team members, the project manager schedules a video conference call.
Which conflict resolution technique does this statement demonstrate?
At a weekly project status meeting, a key team member expresses concerns about the overall approach documented within the project management plan. The project manager is surprised because the team is in the process of executing an important component of the project and the concern has NOT been raised before.
What steps should the project manager take?
During the execution of a project, a key team member is concerned with the overall approach documented in the project management plan. The member surprises the project manager with negative comments about the approach during a weekly status meeting.
How should the project manager address the team member’s concerns?
Three project teams are working on parts of a single project. The parts are highly dependent on each other. The leader of the team indicates that this might create conflicts when the outputs from the three teams are combined.
What guidance should the project manager offer to the team lead?
The atmosphere is tense in the sprint planning review. The agile team members are visibly unhappy—one of them kicks a chair and shouts at the product owner, “That just doesn’t make sense!”
Which two actions should the project manager take in this situation? (Choose TWO.)
A Scrum innovation team is funded at varying levels by six (6) market units. Four (4) niche market units complain they are neglected because the team prioritizes mainstream unit goals. The marketing director suggests devoting a constant 40% of the team effort to the four (4) niche units in a balanced way.
How can the team support this request?
A project manager is leading a technical team that has worked together on several previous projects. However, the current project requires a new coding language that only two of the ten members are proficient in. The project manager wants to build team capability while ensuring the project stays on schedule.
What is the most effective way for the project manager to build the team in this scenario?
A product owner repeatedly complains, saying that a function developed by the development team does NOT seem to align with the original design.
What will help to solve this issue?
A team misunderstood one product functionality documented in an earlier stage of the project. During the current iteration, the functionality has NOT yet been developed, but a business representative has mentioned the deficiency.
How should the project manager proceed?
A project team is currently in the middle of a critical sprint for a high-visibility product launch. A sudden change in corporate security policy requires all project data to be migrated to a new, more restrictive server environment by the end of the week. The team reports that this migration will take approximately two days and will prevent them from finishing the high-priority features promised for the launch.
What is the best way for the project manager to handle this impediment?
During a meeting, a project manager learns that a business result needs to be delivered in four (4) weeks, although the original schedule stated sixteen (16) weeks. The project manager also hears that there is NO available technical resource. The project manager knows the technical resource manager because they worked together on a previous project.
What is the first thing the project manager should do?
Project D is working virtually because of a recent natural disaster. Several activities are delayed because a project team member has NOT been working for the past week. This impacts the critical path.
How should the project manager respond to this problem?
A new project manager needs to deliver a high-stakes agile project. The vendor working with the team is in another country. Though this vendor has delivered excellent quality work on time in the past, they are currently behind schedule. The team explains to the project manager that their attempts to get the vendor back on schedule have failed. They have sent emails and phoned, but the vendor only gives vague, noncommittal responses. The product owner insists that this vendor is essential to the success of the project and an important partner of the business.
Which action should the project manager take?
Several items remain in the Kanban blocked column despite the team’s efforts to resolve the issues. The retrospective reveals that all of the impediments relate to mandatory corporate business processes, which introduce wait times.
What should the project manager do next?
Several unforeseen impediments suddenly appear on the Kanban board in a hybrid project. Each team member has reported one or more different problems relating to a regulatory specification issued by the predictive track.
Which parameter is likely to be highest in the risk assessment?
A project manager is leading a global virtual team with members in three different continents. During a mid-project review, the project manager notices that team members in one specific region are rarely contributing to the shared digital brainstorming board and often remain silent during video conferences, despite being high performers in their individual technical tasks. What is the best action for the project manager to take to support this virtual team’s engagement?
In a product demo meeting, an engineering specialist presents the latest test-driven development prototype and asks for team feedback. Team member Y interrupts the demo to protest about the high cost of the prototype. Members of the engineering team immediately become defensive and begin answering all at once.
What action should the project leader take in this situation?
A project team is being sent overseas to lead an integration project at a subsidiary factory. To prepare, they review a transcript from the retrospective from a previous trip to identify the main problems.
Which problem listed below can the team approach and potentially solve using servant leadership and active listening during the next iteration?
A project manager is leading a high-stress phase of a multi-million dollar infrastructure project. During a status meeting, a senior architect becomes visibly angry and shouts at a junior engineer regarding a design flaw. The rest of the team becomes silent and uncomfortable, and the meeting’s productivity halts. Applying the principles of emotional intelligence, what should the project manager do first?
Project team members are concerned that a new resource does NOT seem suitable for an assigned task.
How should the project manager respond to this concern?
A project manager notices that team member A seems more unhappy after every team meeting. After looking into the situation, the project manager finds out that team member A is not making progress on a key activity. This has an impact on the critical path. Team member A also feels that they are NOT in the correct role within the project team.
What should the project manager do?
A project manager receives complaints from a project sponsor because of a delay in developing a prototype. The project manager consults the resource management plan and responds that the delay was due to a lack of knowledge in a specific skill that was needed by the cross-functional project team.
How can the project manager perform this task better in the future?
A project manager wants to know whether an agile team possesses a good combination of T-shaped skills.
What can the project manager measure to determine this?
A recently formed agile team is exhausted after working 12-hour days to fulfill sprint commitments.
Who has NOT properly performed their duties in this situation?
A project manager has drafted a project management plan. While working with the stakeholders, the project manager observes that the key stakeholder’s priorities for the scope and schedule are vastly different from the priorities of all of the other stakeholders.
Key stakeholder – site upgrades and user improvements in a 9-month project schedule
Stakeholders F, K, and S – user improvements in a 3-month project schedule
Stakeholder A has openly stated that the broader scope and longer schedule are necessary for project success.
What should the project manager do first in order to get this project management plan approved?
A project manager is negotiating a contract with a critical third-party vendor for a specialized component. The vendor is insisting on a “Cost Plus Fixed Fee” (CPFF) contract due to the high level of technical uncertainty. However, the project’s internal sponsor has strictly mandated a “Firm Fixed Price” (FFP) contract to minimize budget risks. The negotiation has reached an impasse, threatening the project timeline. What is the best way for the project manager to resolve this negotiation and reach an agreement?
Project manager A identifies three critical risks with probability of a high impact on the schedule and budget of project A—this project is producing critical deliverables for the company.
The team meets to devise a solution for the risks and decides that three specific resources will be required to address the risks. However, these resources are already committed to a separate project, which is managed by project manager B.
Which party should the project manager work with first to find a solution?
A key stakeholder voices a concern during the planning stage about whether the available resources are adequate to meet the objectives of the project. After further discussion about the requirements and the number of resources identified, the project manager is hesitant about the original plan.
Which two steps should the project manager take next? (Choose TWO.)
The sales and marketing director at company A reports a 40% drop in revenue and significant increase in returns for Widget version 6.0. Customers are complaining directly to customer service and the social media teams report a high rate of negative feedback.
The project team is already working on Widget version 6.1., which is a small set of upgrades and bug fixes. The director gets in touch with the team, requesting a full disclosure of the version 6.0 and 6.1 requirements.
How should the project manager interact with this stakeholder?
The project sponsor is NOT convinced that an agile track should be used in a new R&D project because the company needs to be certain that specific features will be ready for mass production by a specific date.
Which three agile methods can ensure that the sponsor’s needs can be fulfilled in a hybrid project approach? (Choose THREE.)
A project manager is leading a complex organizational restructuring project. One of the department heads, who is a key stakeholder, has missed several recent coordination meetings and has not provided the required input for the project’s resource allocation plan. During a chance encounter in the hallway, the department head mentions they are feeling overwhelmed by their daily operational duties and find the project’s documentation requirements too burdensome.
Which action should the project manager take to improve collaboration with this stakeholder?
A project team leader is reading feedback from a survey given to key functional manager roles. The project aims to introduce a new service to improve an internal process that will affect all of them. One of the questions was “What do you hope to learn or gain from this project?” The answers varied widely among the four team members.
Manager J – I am excited to learn about the new technical service and add it to my team’s core competencies.
Manager K – I want to learn how the new service can help my team do their job better.
Manager H – Maybe not much. I already know how this service is supposed to work.
Manager M – I’m not sure. I’ll wait and see.
How should the project team leader support the growth and development of this group?
A project manager is leading a high-priority transformation project. A senior director from the finance department, who is a critical stakeholder, frequently pushes back against the project’s iterative release cycle, insisting that all financial impacts must be known upfront. The project manager realizes that the director is accustomed to traditional waterfall projects and is uncomfortable with the uncertainty of agile delivery. What is the BEST way for the project manager to mentor this stakeholder?
A key team member is asked to move to another project during the middle of a technical project. The team believes this is an unwise move and expresses concern.
Which action will help to resolve the issue?
A project manager in an organization that uses traditional project management is assigned to an ongoing project. Recently, the organization has started to use agile methodologies for projects. The project manager hears that some team members think key subject matter expertise is missing and that the team does NOT collaborate enough.
How should the project manager respond to these team members’ concerns?
A new resource joins a working project team and is assigned to a small project that is critical to a larger program milestone. Unfortunately, the new resource is under-skilled and very nervous. The team dynamic has become awkward, and work has slowed on the small project.
Which are two possible ways for the project manager to handle this situation? (Choose TWO).
User testing on the last product release revealed low user interest in certain features that required a significant effort to develop. The team feels demoralized, and they want to make sure their future efforts are worthwhile. Success in the next iteration is critical as the competitor product is gaining market share.
How should the team respond?
A project manager is leading a transition from a legacy database system to a cloud-based architecture. During the execution phase, the project manager realizes that while the development team is highly skilled in the old system, they lack the specific cloud security certifications required by the organization’s compliance department. This gap poses a significant risk to the project’s upcoming audit.
What is the best way for the project manager to handle this situation?
A project is started with an approved scope.
As the team implements the project design, a team member states that the product will NOT meet the requirements in certain situations. Correcting the issue increases both scope and costs, and the project will also miss the deadline.
The project sponsors do NOT have additional funding to support the project.
What should the project manager do first?
A project manager works for a company that is preparing to develop a new product. The new product will require skills that are NOT currently available.
To initiate this project, what should the project manager do?
A project sponsor is risk averse and is therefore concerned about negative impacts on the project. To help with this concern, the project team identifies four (4) project risks and then evaluates both the probability of occurrence and the impact of the risk if it occurs. The team uses a 1-5 scale (1 is the lowest and 5 is the highest).
RISK PROBABILITY IMPACT
A 1 5
B 4 4
C 2 5
D 2 2
Based on the table in what order should the project manager rank these risks for risk management purposes?
Although the sponsor and project team say that the new project has an adequate budget and realistic schedule, the project manager worries that unplanned events could threaten the project’s success.
What should the project manager do first?
The project sponsor requires a project team composed of resources that live in four (4) different time zones, working in four (4) different locations. The project sponsor did NOT consider the challenges created by this requirement and believes that the dispersion will provide an ideal project team that will save costs.
Where should the project manager document this in the project charter?
During a conversation with a friend, a project manager hears that union action may occur within the next two (2) weeks. The project manager knows that at this stage of the project, any project delays could cause substantial harm to both budget and schedule, and any union action will affect the project team.
Earlier, the probability of a union action was considered minimal. Thus, it was unanticipated. Also, the project manager has worked successfully in the past with the union.
How should the project manager respond to this issue?
A customer’s end users have NOT completed the required training. The project manager must consider the risk it poses to the timely completion of the project. End user training is a required project deliverable.
Which action should the project manager perform?
A team member has taken unplanned leave during the execution of a project, causing the project team to reschedule some tasks. As a result, critical activities are now occurring at the same time.
What is the first thing the project manager should do?
While a project manager is preparing the monthly project status report, four (4) new risks are identified. These four (4) risks could affect key milestones.
What should the project manager do before presenting this new risk information?
After the start of a project, the project manager learns that an expected governmental subsidy may NOT be available.
How should the project manager address this issue?
After missing two (2) consecutive major deadlines because of delayed glass deliveries, a manufacturing company changes its glass supplier to meet production deadlines. Three (3) months later, production reports quality problems with the new glass. The project manager determines that the supplier change caused quality problems.
How should the project manager avoid this issue in the future?
An agile team has identified several risks during their last retrospective, including the chance of hiring a contractor to double the speed of a critical investigation during the next iteration.
How should the team classify this risk?
An agile project team is working on a high-growth mobile application. The team identifies several technical risks that could impact the stability of the platform as the user base expands. To ensure these risks are managed iteratively, how should the project manager guide the team?
A project has the following characteristics:
– To determine what product should be created, a feasibility study was conducted.
– A change request was approved to develop another product that contradicts the original requirements.
– Data analysis was conducted before the change request was approved.
Which action should the project manager take?
During estimating, the team is discussing an item in the backlog. It becomes clear that the item can be done in different ways, but the best way is NOT obvious.
What should the team do to progress on this item?
A project manager is consolidating several subsidiary plans, including the Risk Management Plan, the Schedule Management Plan, and the Cost Management Plan, to create the final Project Management Plan. During this integration, the project manager notices that several risk response activities—requiring both specialized labor and financial resources—were identified in the Risk Register but have not yet been incorporated into the project’s schedule or budget baselines. What should the project manager do FIRST?
A client’s employee asks the project manager for an additional, new product feature during a status meeting.
To which document should the project manager first refer to determine who has the authority to approve this request?
A project sponsor asks the project manager to change production materials because these materials could cause health problems to consumers.
Which step should the project manager take?
A project manager recently joined a new project with the following characteristics:
– Tight deadlines
– Global virtual team
– Fixed budget
During the planning stage, the project manager wants to avoid scope creep and keep the team focused on delivering a product that meets requirements.
The project manager should ensure __________. (Fill in the blank with the correct response.)
A worldwide product launch will likely be delayed by the lengthy analysis needed to assess the impact of new European Union (EU) regulations. Perishable ingredients and factory bookings are at risk of being lost. The executive committee decides to postpone the launch in the EU but maintain launch dates in all non-EU countries.
How should the project manager re-plan the project to support both launches?
A project manager joins a project with the following features:
-Globally distributed team
-Fixed budget
-Very tight deadlines
How can the project manager avoid scope creep and keep the team focused on delivering a product that meets requirements during planning?
An organization’s policy states any change requested on a project that exceeds a certain amount and/or complexity must adhere to the organizational policy and procedures.
The project manager just received an urgent change request (CR) from the customer, and they want it added to the change control board (CCB) agenda scheduled for tomorrow. However, the CR is incomplete.
What should the project manager do?
A project manager is leading a multi-million dollar construction project in the middle of the execution phase. The main project sponsor requests a significant change to the internal layout of the building to accommodate a new line of business. The sponsor emphasizes that this change is critical for the organization’s long-term strategy and must be implemented as soon as possible. What should the project manager do NEXT?
A project manager begins to prepare the project management plan after receiving the project charter.
There is currently NO historical information in the project management office (PMO).
What next step should the project manager take in this scenario?
A consultant has advised an IT director to use a development and operations (DevOps) approach to a migration project. The IT director wants to understand how the necessary speed can be achieved in a safe way.
Which two examples could demonstrate how DevOps can reduce incidents and speed up deployment at the same time? {Choose TWO.)
An emergency vaccine roll-out project should be deployed to vaccination centers as soon as confirmed locations are booked. Factors such as delayed batch shipments, safety protocols, and target age groups may block the deployment at the last minute. However, the deployment process does NOT vary after passing the tollgate to begin setup at a new location.
Which project approach would best support the goal to maximize the number of centers deployed?
A new wildlife reserve project will have a staff of approximately 80 experts, builders, and logistics workers with exposure to various safety risks. The project manager wants a scalable approach combining flexibility and team dynamics with traditional safeguards.
Which option could be used to tailor a hybrid project of this nature?
A medical equipment vendor is running a hybrid project which includes some custom software development by an agile team. The team progress is good, but slow customer approval causes unnecessary delays. The customer insists that approval can only be given after repeating all the test cases in the target environment.
How can the project manager accelerate the approvals and build customer trust at the same time?
A team is developing the human resource (HR) module of an enterprise resource planning (ERP) system. During a site visit, the client observes concerning data on the team’s information radiators. The burndown chart depicts the progress of the current 3-week iteration. The team is one-third of the way through the iteration, but the actual progress to date reflects the team is behind the planned progress.
The client expresses concern and asks the team lead to discuss it with the product owner. How should the team lead respond?
After months of information gathering and meeting with the community, a police force wants to design and launch an app to improve the quality of communication with members of the public, one of their critical stakeholders.
How is this an example of continuous process improvement?
An organization is initiating a project to develop a groundbreaking consumer medical device. The hardware components of the device require strict compliance with established safety standards and involve a long manufacturing lead time with fixed costs. However, the software interface and user-facing applications are expected to evolve rapidly based on clinical trial feedback and user testing. Which project methodology should the project manager recommend for this project?
A project manager is leading a high-visibility initiative that involves multiple departments with competing priorities. During a recent steering committee meeting, it became clear that there is no consensus on how critical decisions regarding resource allocation are escalated or who has the final approval authority for significant changes. What should the project manager establish to resolve this ambiguity?
A project has the following characteristics:
– A functional manager is also a project stakeholder.
– The functional manager has time constraints and delegates project responsibilities to someone else on the functional team. This person becomes a new stakeholder.
– The new stakeholder is NOT attending meetings.
How should the project manager engage this new stakeholder?
A small group of users complains during a project’s user acceptance stage, stating that their expectations are NOT met.
Which action could help avoid this issue on future projects?
A project manager is creating an agenda and presentation materials for a kick-off meeting that will involve stakeholders across the globe.
How can the project manager facilitate and optimize stakeholder engagement?
Two (2) users complain during the project’s user acceptance stage, saying that their expectations were NOT met.
How could the project manager avoid this issue in the future?
A company is struggling to define the scope of a new project that has multiple phases with a high level of dependency between the phases.
How should the project manager approach this challenge?
During an agile project, key stakeholders are expressing concerns about their lack of involvement. They feel disconnected from the project. The product owner agrees with these concerns and wishes to do something quickly. The iteration is coming to an end.
What would be a good way to engage the key stakeholders at this stage?
A project manager shifts to an agile approach for a project with an aggressive go-to-market time line. The project manager needs to revise the stakeholder engagement plan so that it follows agile principles.
Which action should the project manager take?
An agile project team is mid-way through a product development cycle. A key business stakeholder complains that while the product roadmaps are clear, they are not seeing enough evidence of the actual software being built, leading to a loss of trust in the team’s progress.
What is the most appropriate way for the project manager (or Scrum Master) to address this stakeholder’s concern?
A client brings a project manager into a project during the project’s execution stage.
The project manager reviews the project scope for cost estimating purposes and notices that some deliverables were missed in the work breakdown structure (WBS).
Which step should the manager take next?
A project manager is working with a customer who repeatedly submits requests for new requirements for an existing software product.
The project manager has already provided the completed scope definition for the product’s next version release to stakeholders.
Which step is appropriate for the project manager to take next?
An empowered agile team showed impressive progress in the first four iterations, but now the product owner has noticed low output in the latest five iterations without any apparent reason.
What could be the cause of this situation?
A merger of two companies results in combining an agile software project and a predictive electronics project into a single hybrid project. Two months later, requirements have changed in both tracks but NEITHER has a full picture on status or importance of the requirements.
How can the project manager best resolve the problem?
An agile project team is in the middle of a two-week sprint. A senior executive, who is a key stakeholder, approaches a lead developer and requests a “minor” addition to a feature currently in development. The executive explains that this small change will significantly improve the user experience and should only take a few hours to implement. The developer, wanting to be helpful, is about to start working on the request. What should the project manager (or Scrum Master) do FIRST?
A project manager is leading a large infrastructure project using a predictive (waterfall) methodology. The team has completed the Work Breakdown Structure (WBS) down to the work package level. During a review session, a vendor who will be executing one of the work packages states that the title of the work package is too vague to determine the technical requirements, quality standards, and specific deliverables required. What should the project manager provide to the vendor to clarify these requirements?
A project manager needs to ensure that the team delivers business value within the required timelines. The project manager recently learned that key stakeholders are worried that the current release plan will NOT meet urgent business needs.
How can the project manager effectively respond to stakeholder concerns?
During one daily standup meeting, team members suggest that rework is being caused because there seems to be too much work.
How should the project manager respond to this?
A travel company wants to create smartphone applications for their users. Competitors are racing to do the same. The product owner’s vision describes several versions of the app: Basic, Basic Ad-free, Pro, and Premium.
Which project approach is best suited to the company’s needs?
The marketing director wants to be first-to-market, to launch a version of a smartphone shopping application for retired people, and has asked the agile team to develop it.
What should the project manager do to begin the development process?
The pandemic has caused delays which will make it very difficult to launch the new product on time. Television ads for the launch date are already purchased, so the CEO has asked the project manager to find a way to launch the product even if some minor features are NOT included.
Which measure would be the most effective step toward a successful and timely product launch?
A large financial services firm is developing a new mobile banking platform. The original project plan is based on a predictive (waterfall) approach with a single “Go-Live” date scheduled for 14 months from now. Eight months into development, the Marketing Director reports that a competitor has launched a similar app with a revolutionary peer-to-peer (P2P) payment feature, causing a significant drop in the firm’s new account sign-ups. The firm needs to respond to this market shift immediately to protect its business value. What is the project manager’s BEST course of action to deliver business value with the required urgency?
A textile development project needs a specialized resource to work for 900 hours. The company has decided to outsource these hours. Because of internal policies, all potential service providers must be given the same information about the requirements.
Which action should the project manager take to ensure this?
Near the end of a manufacturing project, several team members are transferred to another project. To complete the work, the project manager needs to acquire additional resource support from a new supplier but is concerned about the cost risk of using a new supplier at this advanced stage of the project.
Now, the project manager needs to work with the procurement team to establish specifications and type of contract to be used.
What should be done?
A deliverable does NOT meet the agreed-upon quality specifications and is rejected by the customer. After investigation, the project team finds a fault with the vendor-provided parts. This fault caused the issue. The vendor says that they CANNOT correct the situation.
What should the project manager review before deciding on next steps?
A project manager is preparing to procure high-end server hardware for a data center expansion project. The technical specifications for the hardware are extremely detailed, and the deliverables are clearly defined and understood by potential vendors. The project manager’s primary goal is to minimize the risk of cost overruns for the organization while ensuring the vendor has a clear incentive to deliver the equipment on time. Which contract type is most appropriate for this procurement?
A project that should have been 90% complete by now is only 65% complete. The total project budget is US$120,000 and the actual cost spent to date (AC) is US$80,000.
What is the scheduled performance index (SPI) and cost performance index (CPI) of this project?
A project has the following characteristics:
– US$3 million budget
– Planned value of US$630,000
– Actual cost of US$650,000
– Earned value of US$540,000
Which statement is true about the current status of the project?
A project that should have been 70% complete by now is only 55% complete. The total project budget is US$210,000, and the actual cost spent to date is US$162,000.
What is the scheduled performance index (SPI) and cost performance index (CPI) of this project?
Over the past six months, the cost per story in agile project A has risen by more than 250% due to a faulty platform which is no longer supported. The project will exceed the budget increment threshold at the next iteration.
Who should decide if the project should be cancelled?
A project manager is overseeing a multi-departmental software rollout. The project schedule is aggressive, and several key developers are being shared with other projects, creating several resource over-allocations. The project manager needs to address these conflicts but has been strictly told that the project’s critical path and finish date cannot be changed. Which technique should the project manager apply?
A project manager is overseeing a multi-departmental software rollout. The project schedule is aggressive, and several key developers are being shared with other projects, creating several resource over-allocations. The project manager needs to address these conflicts but has been strictly told that the project’s critical path and finish date cannot be changed. Which technique should the project manager apply?
A project manager is presenting the monthly performance report to the steering committee. The report indicates that the Cost Performance Index (CPI) is 0.75 and the Schedule Performance Index (SPI) is 1.3. How should the project manager interpret these results regarding the health of the project?
A project has the following characteristics:
– A quality management plan is in place.
– The quality management plan states that project deliverables must be reviewed, at a minimum, 1.5 weeks before the deadline.
– Four (4) deliverables have missed this quality requirement.
Which step should the project manager take?
The project is overseen by a senior project manager. A new project manager joins the project, and the sponsor asks the new project manager to develop the quality management plan.
How should the new project manager proceed?
During sprint planning, some new backlog items are prioritized but NOT estimated. The product owner requires a new set of tests to verify the unique properties of the items.
What should happen before adding it to the sprint backlog?
A start-up company needs to quickly expand its product portfolio to meet market demand. Recently, staff members are working on two or three agile teams, each dedicated to a different product line. Output is dropping and defect rates are rising in all teams.
In which two ways can the project manager help the agile teams improve their work? (Choose TWO).
An agile team is nearing the end of the project and has been able to complete all stories and deliver value to the client. However, the coach has noticed that the coding standards are NOT up to par.
What should the team do?
A project team lead has challenged the team to minimize defects and waste in project teamwork. As an initial step, the team proposes to assess the relevant quality standards and framework.
How can the team do this?
A project team is building a pedestrian sky bridge across a major river. Some technical project team members are highly experienced with mega infrastructure projects. However, the team also includes many junior trainees who have little experience. This variance in team experience is listed as a risk that could affect team working conditions and safety, as well as the project build quality.
At the team’s morning status meeting, a facilitator led a discussion about continuous improvement and asked the team how leadership and the company could help them improve.
The team listed the five following answers. Which two actions can help this team improve? (Choose two)
A project manager for a high-end electronics manufacturer is conducting a quality audit on the assembly line processes. The goal is to determine if the team is adhering to the established organizational policies and to identify any process gaps that might be causing minor defects in the final units. Which process is the project manager currently performing?
A company is planning to utilize a new product that leverages innovative technologies and processes.
The project manager has verified that the component work packages have been defined, and constraints for each component have been identified.
Which estimating technique should the project manager use to obtain a precise cost estimate of the project?
A project manager is uncertain about the duration of a new project and consults several groups of subject matter experts (SMEs). The first group advises that development can be finished in 29 days. The second group identifies some risks that could make the duration up to 46 days. The third group proposes a new development method that can shorten the time to 18 days.
Using the Triangular estimation technique, what is the estimated development duration for the new product?
A trend of stories is INCOMPLETE, and this becomes apparent at the end of iterations. Several team members worked on these stories and NO blockers were identified.
How can the agile team resolve the situation?
An agile project is structured without timeboxing. Tasks are grouped by high-level goal but CANNOT be predictably scheduled.
In which three ways can the work be distributed for efficient execution? (Choose THREE).
Six months into a strategic agile project, company executives are closely monitoring its progress. The COO expresses frustration that the last weekly burndown charts show the projected completion date significantly moving back and forward several times.
How can the project manager forecast the completion date with more accuracy and certainty?
A start-up has grown quickly, and there are now four (4) agile teams working on interrelated products. All teams have begun to experience impediments and gaps related to work in other teams.
How should the project manager address this problem?
A hybrid virtual reality project is running an agile software track and a predictive electronics track. Halfway into the project, delays are accumulating due to misaligned deliverable releases between the two tracks.
Which two elements should the project manager combine to produce a common network diagram? (Choose TWO).
At a company party, people are having a friendly, open conversation about which team is the fastest. One person laughs and says that team A has a velocity of 20, whereas team B has a velocity of 40, so team B members will all be receiving bonuses.
How should the leader of team A react?
A project manager is developing a schedule for a new commercial building. The project plan shows that the concrete foundation must be poured before the steel framing can begin. The technical specifications state that the concrete requires five days to cure properly before it can support the weight of the steel structure. How should the project manager represent this five-day curing period in the project schedule?
A project is delayed because the deliverables are NOT of acceptable quality. A change is required.
First, the project manager issues a formal change request and communicates the change to all stakeholders. The stakeholders are NOT satisfied with this. They want a more detailed report about the nature of the delay.
What should the project manager do next?
A project’s single sponsor has been replaced by a steering committee due to a significant increase in project size.
How should the project manager approach this change?
A governmental agency becomes a key stakeholder on a complex project due to regulatory changes. In light of the change, the project manager needs to develop an understanding of this new stakeholder and identify any new high-level risks that may result from the change.
Which two options should the project manager use? (Choose TWO).
A project team has set up an unofficial online communications platform to enhance communication.
The project manager was NOT aware that this platform existed until recently, after learning that its use has facilitated some activity that a stakeholder finds concerning.
Which action should the project manager take?
After a project delay, the project manager determines that a change is needed to the product deliverables in order to ensure quality. The project manager takes the following steps:
1. Issues a formal change request.
2. Communicates the change to all stakeholders.
3. Receives feedback that the communications approach did NOT meet stakeholders’ expectations.
What should the project manager do next?
A security-classified, agile software project requires outside expertise and delivery to add a module based on machine learning. An approved supplier asks the project manager to join the daily meeting with the supplier’s agile team, but the project manager’s schedule is too full with internal meetings.
How could the two teams synchronize interactively but somewhat less frequently?
A smart grid project combines predictive and agile tracks. The agile team detected a major software defect after its release and began working on a correction. But the defective release was deployed by the predictive track, and this caused a field test to fail.
Which measure would be most effective to prevent similar problems in the future?
A project manager is overseeing a global construction project. A critical safety update regarding heavy machinery operation must be implemented at all sites immediately. The project manager sends an urgent email to all site supervisors worldwide. Two days later, an incident occurs on a remote site. The supervisor there claims they never saw the email because their inbox was flooded with administrative requests.
What should the project manager have done differently to ensure effective communication in this high-stakes scenario?
An agile team has been asked to update the project artifacts because new team members are joining soon. Which two of the following should be updated? (Choose two)
A project manager is overseeing a complex regulatory compliance project with a team of 50 people across three locations. During a quality audit, it is discovered that different team members are using outdated versions of the requirements documentation and inconsistent templates for status reporting. This has led to conflicting data being presented to stakeholders. What should the project manager implement to resolve this issue and align with the requirements for managing project artifacts?
The team working on Project A has resolved a technical issue, and the project is moving forward. The project manager has been warned that the same issue will probably arise on similar projects in the future.
What should the project manager do first when responding to this warning?
A construction project to build a luxury skyscraper is coming to an end. In advance of the handoff, the management team has been trained to take charge of all aspects of maintaining the building. The lead engineer from the development team expresses concern. During construction, substantial new technologies were introduced, and the engineering team learned new skills.
What is the best way for the team to handle knowledge transfer in this case?
Company H is completing a merger and has acquired several valuable assets from company Z that require specialist care, including intellectual property rights and museum artifacts. The team is conflicted about what to do, but the product owner has identified knowledge transfer—to ensure the new organization can maintain the collections properly—as one of the highest priorities for the merger.
Which two of the following actions should the team take? (Choose two)
A large project includes functional groups in four (4) countries, a steering committee, and a project sponsor. As the project approaches completion, the project manager must prepare the closeout documents.
How should the project manager obtain appropriate signoff on the acceptance of project deliverables?
A project manager has completed the following steps:
– Finished a major IT deployment project
– Confirmed with the release manager that all systems are working
– Confirmed that functionality has been verified by the quality assurance team
– Informed the customer
Which next step should the project manager take?
Review the following project characteristics:
– The project is in the initiation phase.
– Due to lack of funding, the project is terminated.
– The project manager must close the project.
What is the first action the project manager should take?
Project team members are spending a lot of time helping maintenance and operations staff with a recently commissioned project component.
The project manager needs to validate that the component was signed off and ownership transferred.
Which three (3) documents should the project manager use for this decision?
At the end of an agile project, all stories are completed on schedule and all tests passed, but the customer does NOT consider the product a success.
Which is the most effective way to prevent this outcome in future projects?
A project manager receives the following for a new project:
– Assumptions
– Restrictions
– Preliminary scope
After receiving this information, what should the project manager do first?
A key project resource is discussing the complexity of project deliverables with the project manager 2 weeks before the kickoff call. The resource expresses nervousness and concern regarding the deliverables.
The project manager wants to ensure that the deliverables are realistic.
What is the appropriate action to take?
A new product development project is to be initiated in a difficult business context. Competition is driving prices down, and supply costs are rising.
Why would an agile incremental project approach be the safest choice in this context?
An agile innovation team is highly productive. However, the Head of Operations informs the product owner that the company is NOT getting sustainable return on investment from the team’s work.
How should the product owner address the problem?
A project to implement a new customer relationship management (CRM) system designed to increase customer retention by 15% is approaching completion. The project manager is preparing to transition the final deliverables to the operations team. To ensure that the project’s business value and benefits are properly evaluated and realized over the long term, what is the project manager’s most critical action?
A new law is expected within the next 6 months that will affect a business’ product line. The next product is launching and should be completed within 3 months. Unfortunately, the new product will NOT meet the requirements of the proposed law.
How should the project manager respond to this potential problem?
A project manager needs to ensure that all data security requirements are covered during a data warehouse development project’s execution phase. Each of the databases created during different project phases will have a specific data security policy to comply with governmental data security laws.
How should the project manager plan to meet these requirements?
A Canadian start-up company announces to the press its imminent launch in the European Union (EU) and Latin America. Soon afterward, the compliance team recommends delaying the launch by 6 months to avoid substantial penalties related to a new set of EU regulations.
Which approach could the project manager take to advance the launch project while preparing the compliance measures?
The legal team informs the product owner that another company owns a patent for an innovation used in the agile team’s product, which is now 75% complete.
What should the product owner do to determine the appropriate way forward?
A medical charity organization operates in disaster emergency zones worldwide. At headquarters, the leadership wants to ensure that their practitioners’ professional licenses are compliant with governing bodies both in the practitioner’s home and in their working locations. This is a condition set by their board of directors and the charity’s legal team.
In order to facilitate the new measures, which three actions should be taken? (Choose three)
A project manager is leading a global data center migration project. During the execution phase, the legal department informs the project manager that a new data privacy law has been enacted in one of the regions where the project operates. The law requires specific encryption standards that were not included in the original technical specifications and will likely affect the project’s timeline and budget. What should the project manager do FIRST?
An agile team needs to decide who should represent them in the Scrum of Scrums.
Which option should be used to select the best-suited team member?
A project manager is leading a large-scale organizational transition from a traditional manufacturing model to a digital-first automated facility. During the middle of the project, the project manager identifies significant resistance from mid-level supervisors who fear their roles will be eliminated by the new automated systems. This resistance is causing a slowdown in information sharing and is affecting the project schedule. What is the BEST way for the project manager to support this organizational change?
Over the past six months, the development cost per story has risen by more than 250% due to a faulty platform which is NO longer supported. The product vision highlights unique features of the platform as a pre-requisite for the product.
What should the project manager do to determine next steps?
The quarterly results show that competitors are driving prices down. The company is losing market share and midway into a product development project, it appears the sponsoring unit is not likely to get return on their investment.
Which two actions should the project manager take to adapt the project to these new conditions? (Choose TWO).
During a sprint review, the team identified successful gains on planned improvements while noting that a lot more development and testing is required. The product owner wants to report on the business value of the work.
Which action should the team take to assist the product owner with validating business value?
A project manager is overseeing the development of a next-generation smartphone. Six months into the project, a major competitor unexpectedly announces a new device that includes a disruptive battery technology that provides double the life of the battery currently planned for the project. This technology shift is expected to significantly diminish the market appeal and perceived value of the project’s final product. What should the project manager do FIRST to address this external environment change?