Now that you have finished reviewing all course material, it’s time to take the final exam. You must score 70% or higher to pass this exam. You will have an unlimited number of attempts to pass and there is no time limit for each attempt. Once you pass, you will receive a certificate of completion. Good luck!
0 of 16 Questions completed
Questions:
You have already completed the quiz before. Hence you can not start it again.
Quiz is loading…
You must sign in or sign up to start the quiz.
You must first complete the following:
0 of 16 Questions answered correctly
Time has elapsed
You have reached 0 of 0 point(s), (0)
Earned Point(s): 0 of 0, (0)
0 Essay(s) Pending (Possible Point(s): 0)
You must score 70% or higher to pass this exam. You get unlimited attempts to pass. Please review the course material and attempt this exam again. Once you pass, you will receive a certificate of completion. Click the Restart Quiz button to take this quiz again.
Congratulations – You Passed the Course Exam. Click the “Continue” button to view your certificate of completion.
Which of the following is NOT an example of a business task?
All of the following are characteristics of projects except:
Which of the following business needs would exist because of existing customers requesting a new product, product feature or a new service?
Who is the individual that is responsible for applying knowledge, skills, tools and techniques to complete project activities?
The project manager cannot succeed without the support of the upper management executives of the company.
A __________ articulates the reasoning for initiating a project or phase of a project.
Which area of the business case will typically be read by busy executives?
Which area of the business case will spell out either the recommendation or the decision to be taken?
Which of the following groups are typically responsible for reviewing, selecting and prioritizing projects?
Which of the following is NOT a benefit measurement method for selecting projects?
What project selection method assigns a weighting for different criteria and then scores the criteria for each project?
Which cash flow analysis technique identifies the amount of time it will take to recoup the initial cost of producing the product, service or result of the project?
Which cash flow analysis technique takes into account the fact that money received in the future is worth less than money received today?
Which cash flow analysis technique will allow you to evaluate cash inflows using discounted cash flow techniques?
What organization structure is primarily used in organizations where project work is the primary business of the organization, like a contracting firm or a professional engineering firm?
Organizational process assets are the assets of the organization that are typically obtained as a result of project experience.